INDUSTRIAL MANAGEMENT AND ENTREPRENEURSHIP-OCTOBER-2010


SIXTH SEMESTER DIPLOMA EXAMINATION IN ENGINEERING/TECHNOLOGY-OCTOBER-2010
INDUSTRIAL MANAGEMENT AND ENTREPRENEURSHIP
PART-A
(Maximum marks:15)
v  Answer the following questions in one or two sentences:
1.Define scientific management.
2.What is meant by division of labour?
3.How can define job evaluation?
4.What is ISO-9000?
5.What is brain storming?
6.What is dummy activity?
7.Define nominal wage.
8.Define MBO.
9.What are the contents of management information system?
10.What is meant by industrial psychology?
PART-B
(Maximum marks:60)
(Answer one full question from each unit)
Unit-1
v  (a)Explain the kinds of partners.(6)
          (b)What are the qualities of good leader?.(6)
OR
v  (a)Define:
(i)Authority and Responsibility (ii)Scalar chain (iii)Espirit-De-Corps.(6)
(b)What are the essentials of effective communication?.(6)

Unit-2
v  (a)What are the responsibilities of quality assurance department?(6)
(b)Describe the various benefits of ISO 9000 certification.(6)
         
OR
v  (a)Explain briefly the different techniques of TQM.(6)
          (b)What is brain storming?Describe briefly the methods of brain storming.(6)
UNIT-3
v  (a)Compare between CPM and PERT.(6)
          (b)A project has eight activities,the expected time of each activity is as follows:
Activity
1-2
1-3
1-4
2-4
2-5
3-6
4-6
5-6
Expected time Duration(weeks)
6
8
5
3
5
12
8
6
Identify the critical path and project duration.(6)
OR
v  (a)Explain briefly market information system with block diagram.(6)
          (b)The standard time for a particular job is 12 hours and the time taken by the worker to complete the job is 10 hours.If the operator is paid at the rate of Rs.30 per hour,calculate the premium under:
(i)Halsey 50-50 plan          (ii)Halsey 33 1/3%plan.(6)
UNIT-4
v  (a)A factory needs three components A,B,C.It requires processes like machining,assembling and testing.The component A requires machining time,assembling time and testing time as 4,1,1 hours respectively.Similarly the component B requires 3,3,2 hours and component C requires 1,1,0 hours.The total available machining time is 200 hours.The profit from A,B,C are Rs.20,50,70 respectively,formulate the LPP for maximum of profit.(6)
(b)Define MBO.Draw a block diagram to represent MBO process.(6)
OR
v  (a)Describe the waiting theory and state its field of application.(6)
          (b)Distinguish between a data processing system and a management information system.(6)
UNIT-5
v  (a)Prepare incremental projects to reduce weakness and threats.(6)
          (b)What are the functions of an entrepreneur?.(6)
OR
v  (a)Explain briefly the various causes of accident.(6)
(b)What are the causes and effects of water pollution?.(6)
        